Structural failure of concrete bulkhead at Castle Point Park in 2024 required installation of new steel bulkhead to support a reconstructed platform deck for the walkway and rebuilding of the park costing $16.3 million
Slide 1: Rebuilt Castle Point Park reopened earlier this year; Slide 2: Castle Point Park boundaries; Slide 3: Concrete seawall section built in 2001.
FBW | August 12, 2026
Stevens Institute of Technology owns Block 259, Lot 2, the land and water area at the base of Castle Point. The land portion is just 1.15 acres, a narrow strip along the 700 and 800 blocks of Sinatra Drive. On January 4, 1995, Stevens President Hal Raveche and Hoboken Mayor Anthony Russo signed their names to a 50-year lease agreement that paved the way for the creation of Castle Point Park. The lease requires the City to pay a nominal $1 per annum.
Six days later, the City of Hoboken granted an easement to the New Jersey State Department of Environmental Protection (NJDEP) restricting the land’s use for a public space “for walkway purposes, being those activities including walking, jogging, bicycling, fishing, sitting, viewing and other like activițies consistent with and compatible with the enjoyment of the waterfront area.” The easement states that the grantee (NJDEP) “agrees to construct all portions of the Walkway which are in the Easement Area and access thereto.”
By October 2000, the state’s Green Acres program and the Department of Transportation allocated $1.35 million for the project. A federal grant added another $1 million. The City of Hoboken provided additional funding.
The construction of Castle Point Park became a joint venture of the City of Hoboken, the NJDEP and the State Division of Buildings and Construction (DBC). On November 30, 2000, the DBC received bids for the construction ranging from $2.8 to $5.6 million. The parties agreed to accept the lowest bid.
In 1988, the State of New Jersey conceived a 30-foot public walk — the Hudson River Waterfront Walkway — that would stretch the 18.5-miles from the Bayonne Bridge to the George Washington Bridge. The requirement for property owners to construct their portion of the walkway was written into the state’s Coastal Zone Management Rules as a condition of their NJDEP waterfront development permit.
In the mid-1990s, Stevens Institute of Technology recognized that there was no development potential for this narrow strip of land. The pile supported concrete decking over the Hudson River was collapsing. The lease arrangement relieved Stevens from the obligation of building the state-mandated walkway.
As with all Green Acres funding, Castle Point Park was permanently placed on the state’s ROSI (Recreation and Open Space Inventory) for Hoboken. In addition to the walkway, the park included a fishing pier. Later, a skate park was added at the north end.
Rebuilding Castle Point Park
In 2024, a major sinkhole opened up on Sinatra Drive near the skate park, prompting an investigation of the structural integrity of Hoboken’s shoreline. The City hired Colliers Engineering & Design, whose marine engineers used scuba divers, ground-penetrating radar and geotechnical borings to assess the extent to which the structure of the bulkhead (seawall) had failed. Colliers determined that the fill beneath the concrete seawall built by the State of New Jersey in 2001 had been washed away in sections, leaving a void and leading to the further erosion beneath Sinatra Drive.
The March 2026 Coastal Permit Compliance Statement submitted by Colliers describes the extensive work required:
The proposed work consists of the construction of a new steel bulkhead behind the footprint of the existing concrete gravity bulkhead and reconstruction of the platform deck. The steel bulkhead requires augured steel piles grouted into the rock to support the steel sheet piles with shallow embedment due to the rock profile. Due to the configuration of the existing platform with the existing platform deck being supported by the bulkhead (in-shore end), the platform deck shall be demolished, so the upland edge of the platform shall be supported by the new steel sheet pile bulkhead.
In 2025, the Hoboken City Council awarded two contracts to Simpson & Brown that totalled $16.3 million to rebuild the bulkhead and reconstruct Castle Point Park. That same year, the Council awarded a professional services contract to Colliers Engineering & Design in the amount of $950,620 for construction administration and $256,575 for a comprehensive inspection of Hoboken’s waterfront structures. It took a full year to complete the work. Castle Point Park was reopened earlier this year.
Further improvements adjacent to Castle Point Park are scheduled to be completed in the next year as part of the Sinatra Drive Project, from Fourth to Eleventh Streets. This project will add a two-way protected bicycle pathway and narrow traffic lanes to slow traffic. A double row of canopy trees will be planted, transforming the sparse landscape plan that has existed for Castle Point Park since 2001.
Note: FBW’s 1990 Plan for the Hoboken Waterfront expanded on the notion of a public waterfront. Instead of accepting the minimum standard set by the state-mandated 30-foot walkway at the water’s edge, FBW’s vision called for a continuous, public waterfront park with Sinatra Drive providing a clear delineation between the public park and upland blocks for private development.
Related Links
Long-Awaited Improvements at Hoboken’s Waterfront Anticipated by End of 2027
$30 million seawall repair puts Hoboken’s Castle Point Park off limits for most of 2025
Coastal erosion is not confined to New Jersey’s beaches; Hoboken’s shoreline is vulnerable too
The Sinatra Drive Project is an opportunity to upgrade the long neglected central waterfront
Phase 1 of Maritime Park will include a new, state-of-the-art skatepark and a possible “tree nursery”
Plan for the Hoboken Waterfront